DATE:1-Apr-2003
DOY: 091
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:2-Apr-2003
DOY: 092
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following study were imported to the EOF:
cmewatch_5.def
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:3-Apr-2003
DOY: 093
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:4-Apr-2003
DOY: 094
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following studies were imported to the EOF:
ar_so_wa_2.def
ch_so_ov_2.def
ch_so_wa_71.def
qs_so_ov_1.def
qs_so_wa_70.def
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:5-Apr-2003
DOY: 095
OPERATIONS ENGINEER(S): J. Seidel
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:6-Apr-2003
DOY: 096
OPERATIONS ENGINEER(S): C. King
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:7-Apr-2003
DOY: 097
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: S. McIntosh
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
DSN-66 was having network problems while loading the plan. Three
unsuccessful attempts to load, resulted (each time) in command anomallies.
Science plan was finally loaded on DSN-27.
IWS command rate was changed to 1/10s for commanding on DSN-66.
A parity error occured in the Secondary (Science) Processor at memory
location #8007887f.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:8-Apr-2003
DOY: 098
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: S. McIntosh
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
Station lost lock with spacecraft at 20:32 UT during science plan upload.
The science plan was aborted at 20:37 UT. The science plan was later loaded.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:9-Apr-2003
DOY: 099
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: S. McIntosh
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
At 13:45 UT, contact was lost due to nework problems at Madrid (DSN-66), at
12:30 UT. Spacecraft was not placed in record. Data loss will be from 13:45
- 14:05 UT. Data from 12:30 - 13:45 UT will be available from LZ0 CDROM.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:10-Apr-2003
DOY: 100
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: S. McIntosh
CDS INSTRUMENT:
A Mechanism Lubrication was completed at 16:00 UT.
CDS GROUND SYSTEM:
The IWS command rate was reset to 1/3s at 20:19 UT to enable performance of
engineering work.
DAY PLAN: Mechanism Lubrication, Science Operations.
COMMENTS:
=============================================================================
DATE:11-Apr-2003
DOY: 101
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: S. McIntosh
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:12-Apr-2003
DOY: 102
OPERATIONS ENGINEER(S): J. Seidel
SCIENTIST: S. McIntosh
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:13-Apr-2003
DOY: 103
OPERATIONS ENGINEER(S): C. King
SCIENTIST: S. McIntosh
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:14-Apr-2003
DOY: 104
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The IWS command rate was reset to 1/10s to facilitate commanding on DSN-27.
Action taken at 21:57 UT.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:15-Apr-2003
DOY: 105
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The IWS command rate was changed to 1/3s in order to load on DSN-66. It
was immediately reset back to 1/10s for commanding on DSN-27 later today.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:16-Apr-2003
DOY: 106
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:17-Apr-2003
DOY: 107
OPERATIONS ENGINEER(S): C. Maroney
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:18-Apr-2003
DOY: 108
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:19-Apr-2003
DOY: 109
OPERATIONS ENGINEER(S): J. Seidel
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:20-Apr-2003
DOY: 110
OPERATIONS ENGINEER(S): C. King
SCIENTIST: J. Ireland
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:21-Apr-2003
DOY: 111
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher
CDS INSTRUMENT:
Due to ground station problems, the science plan failed to load. Operator
needed to wait until the next station: DSN-46 (1:25-6:20 UT) on DOY 112 to
upload plan. Science plan was modified by removing SYNOP. Science plan was
uploaded at 5:27 UT on DOY 112. Science will resume at 6:55 UT.
CDS was idle from 00:00 - 6:55 UT (DOY 112). Emergency study was appended
to the plan, but was not scheduled to start until 01:00 UT DOY 113.
CDS GROUND SYSTEM:
The following raster duration changes were made:
POBS3 rid/38 var/57 1570s - 1575s
NETWORK rid/10 var/73 3748s - 3835s
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:22-Apr-2003
DOY: 112
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher
CDS INSTRUMENT:
A study (NIMCP) was aborted by another study (FULLCCD) at 23:14:24 UT
(DOY 112). CDS Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:23-Apr-2003
DOY: 113
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:24-Apr-2003
DOY: 114
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:25-Apr-2003
DOY: 115
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:26-Apr-2003
DOY: 116
OPERATIONS ENGINEER(S): R. Yurow / C. King
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:27-Apr-2003
DOY: 117
OPERATIONS ENGINEER(S): J. Seidel
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:28-Apr-2003
DOY: 118
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:29-Apr-2003
DOY: 119
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:30-Apr-2003
DOY: 120
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================