DATE: 1-Apr-2007
DOY: 091
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 2-Apr-2007
DOY: 092
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: A secondary parity error was detected at address #8003c0b7.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 3-Apr-2007
DOY: 093
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 4-Apr-2007
DOY: 094
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 5-Apr-2007
DOY: 095
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 6-Apr-2007
DOY: 096
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 7-Apr-2007
DOY: 097
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 8-Apr-2007
DOY: 098
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 9-Apr-2007
DOY: 099
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: A primary parity error was detected at address #8003f877.
A secondary parity error was detected at address #80001bb7.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 10-Apr-2007
DOY: 100
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: A secondary parity error was detected at address #80043a7b.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 11-Apr-2007
DOY: 101
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 12-Apr-2007
DOY: 102
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: A secondary parity error was detected at address #80075a7b.
A secondary parity error was detected at address #8007bdeb.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 13-Apr-2007
DOY: 103
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 14-Apr-2007
DOY: 104
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 15-Apr-2007
DOY: 105
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: C. Henderson (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 16-Apr-2007
DOY: 106
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 17-Apr-2007
DOY: 107
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 18-Apr-2007
DOY: 108
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: An on-board mechanism lubrication was performed at 22:00 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 19-Apr-2007
DOY: 109
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 20-Apr-2007
DOY: 110
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 21-Apr-2007
DOY: 111
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 22-Apr-2007
DOY: 112
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: M. Marsh (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 23-Apr-2007
DOY: 113
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 24-Apr-2007
DOY: 114
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 25-Apr-2007
DOY: 115
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 26-Apr-2007
DOY: 116
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: A primary parity error was detected at address #800739d7 - 
(SAFE-unused area).
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 27-Apr-2007
DOY: 117
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: A secondary parity error was detected at address #80036c2f.
A reboot is scheduled for Monday.
CDS GROUND SYSTEM: The following study was imported to the EOF:
BLINK_FA (study_id=173/var=14)
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 28-Apr-2007
DOY: 118
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 29-Apr-2007
DOY: 119
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 30-Apr-2007
DOY: 120
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Rainnie (RAL)
CDS INSTRUMENT: A telemetry submode change from submode 5 to submode 6 
occurred at 16:15 UT.
A CDS reboot was performed between 15:54 and 17:45 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================


From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory
Site maintained by John Rainnie.
Last revised on Tuesday (22/Apr/2008) at 21:06.