August 1997
 
==============================================================================
DATE:  01-August-1997
DOY: 213
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: D. Brooks
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  02-August-1997
DOY: 214
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A parity error (SEU) was detected in the primary processor memory space.
  Since the parity error is at a safe location, no reboot is necessary.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  04-August-1997
DOY: 216
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  05-August-1997
DOY: 217
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  CUVMCP went into HIGH ALARM for 4 formats (60 sec.)
  A WATCHDOG error occured at 19:28 UT.  The recovery procedure was completed
  at 21:07 UT and the science plan was restarted at 23:11 UT.  CDS is nominal
  after the recovery.  The GIS patch required reloading during the reboot.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  06-August-1997
DOY: 218
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: Watchdog at 03:40 UT.  Instrument was rebooted at 07:31 UT, 
  and science resumed at 09:00 UT. 
  CTM18 went into high warning today at a value of 36 degrees.
  It stayed there for approximately 30 minutes.  The reason was the study
  G_SPIC_4.  This study runs for 5 minutes and moves the slit mechanism 
  between slits 4 and 6 within those 5 minutes.  The study was altered in 
  order to compensate for the slit motor problem. 
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  07-August-1997
DOY: 219
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  CPT began reuseing CDHSID numbers for sequences due to the maximum number 
  of entries in the rseries_id database table.  The database table size was
  expanded to correct for the problem. 
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  08-August-1997
DOY: 220
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A parity error was detected in the secondary (science) processor memory
  space.  The secondary processor was rebooted.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  09-August-1997
DOY: 221
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  10-August-1997
DOY: 222
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  11-August-1997
DOY: 223
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A parity error was detected in the primary processor memory space.  Since
  the error is in a safe location, no reboot is nescessary.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  12-August-1997
DOY: 224
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A parity error was detected in the secondary (science) processor memory
  space.  The secondary processor was rebooted at 17:02 UT.
DS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  13-August-1997
DOY: 225
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A WATCHDOG error occured at 02:44 UT.  The recovery procedure was completed
  at 04:09 UT and the science plan was restarted at 06:59 UT.  CDS is nominal
  after the recovery.
CDS GROUND SYSTEM: 
  The current FITS disk was changed to /cdsfits13.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  14-August-1997
DOY: 226
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  15-August-1997
DOY: 227
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  18-August-1997
DOY: 230
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  Began implementation of a program divide QKL files into components which
  contain a contigous set of packets.  Contigous QKL files will be written
  to /cdsr2.  Original QKL files will be written to /cdsr1 by the ECS.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  19-August-1997
DOY: 231
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: 
  A WATCHDOG error occured at 03:39 UT.  The recovery procedure was completed
  at 06:24 UT and the science plan was restarted at 06:50 UT.  The GIS 
  software patch required reloading during the recovery.  CDS is nominal
  after the recovery.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  20-August-1997
DOY: 232
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: 
  A WATCHDOG error occured at 08:50 UT.  The recovery procedure was completed
  at 11:14 UT and the science plan was restarted at 14:00 UT.  Due to an 
  error setting study counter, the plan had to be aborted at 18:20 UT and the
  study counter advanced by 5 increments.  The science plan was again resumed
  at 23:23 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  21-August-1997
DOY: 233
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  22-August-1997
DOY: 234
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  23-August-1997
DOY: 235
OPERATIONS ENGINEER(S): A. Hammond
SCIENTIST: B. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  24-August-1997
DOY: 236
OPERATIONS ENGINEER(S): E. Donaldson
SCIENTIST: B. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  25-August-1997
DOY: 237
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  Nominal.  Performed lubrication study.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Lubrication Study, Science Operations.
COMMENTS:
==============================================================================
DATE:  26-August-1997
DOY: 238
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  A WATCHDOG error occured at 12:31 UT.  The recovery procedure was completed
  at 16:16 UT and the science plan was restarted at 17:00 UT.  CDS is nominal
  after the recovery.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  27-August-1997
DOY: 239
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  28-August-1997
DOY: 240
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  29-August-1997
DOY: 241
OPERATIONS ENGINEER(S): C. Haskell / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  A WATCHDOG error occured at 08:30 UT.  The recovery procedure was completed
  at 18:18 UT and the science plan was restarted at 19:00 UT.  During the
  recovery, the GIS instrument latched up and refused to accept commands.
  The GIS was reset by bringing CDS back down to STANDBY mode.
  Due to an operator error, the study counter was not set correctly
  during the reboot.  It was latter reset.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  30-August-1997
DOY: 242
OPERATIONS ENGINEER(S): E. Donaldson/A. Hammond
SCIENTIST: E. Alam
CDS INSTRUMENT: 
  A WATCHDOG error occured at 03:03 UT.  The recovery procedure was completed
  at 04:12 UT, and science resumed at 06:26 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE:  31-August-1997
DOY: 243
OPERATIONS ENGINEER(S): E. Donaldson/A. Hammond
SCIENTIST: E. Alam
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================






From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory
Site maintained by John Rainnie.
Last revised on Monday (13/Aug/2001) at 14:02.