Scientific Operations | ![]() |
|
February 2006
=============================================================================
DATE: 1-Feb-2006
DOY: 032
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Brosius (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 2-Feb-2006
DOY: 033
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Brosius (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 3-Feb-2006
DOY: 034
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Brosius (GSFC)
CDS INSTRUMENT:
A Mechanism Lubrication was performed at 22:00 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 4-Feb-2006
DOY: 035
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: J. Brosius (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 5-Feb-2006
DOY: 036
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: J. Brosius (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 6-Feb-2006
DOY: 037
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following raster duration change was made:
NISAT_W (RID/77 Var/4) 4840s - 5110s.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 7-Feb-2006
DOY: 038
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 8-Feb-2006
DOY: 039
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 9-Feb-2006
DOY: 040
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 10-Feb-2006
DOY: 041
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT:
A Flat Field Calibrations study was performed at 15:00 - 16:45 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 11-Feb-2006
DOY: 042
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 12-Feb-2006
DOY: 043
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: T. Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 13-Feb-2006
DOY: 044
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A Secondary (Science) parity error was detected at address #800767e3.
CDS GROUND SYSTEM:
The following raster duration change was made:
MOSES_2 (RID/82 Var/8) 285s - 295s.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 14-Feb-2006
DOY: 045
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 15-Feb-2006
DOY: 046
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A Secondary (Science) parity error was detected at address #80062217.
A Primary parity error was detected at address #80054057 - This is in the
Science Module (SAFE).
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 16-Feb-2006
DOY: 047
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
GIS raw dumps (detectors 1,2/slit 2) were conducted from
01:52 to 05:00 UT.
GIS raw dumps (detectors 1,3,4/slit 2) were conducted from
20:10 to 23:40 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 17-Feb-2006
DOY: 048
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 18-Feb-2006
DOY: 049
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 19-Feb-2006
DOY: 050
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 20-Feb-2006
DOY: 051
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A secondary memory error was detected at address #8006e90b.
CDS GROUND SYSTEM:
The following raster duration change was made:
TRANSCAN (RID/206 Var/2) 61s - 75s.
DAY PLAN: Science Operations.
COMMENTS: US Holiday (President's Day)
=============================================================================
DATE: 21-Feb-2006
DOY: 052
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 22-Feb-2006
DOY: 053
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 24M Keyhole starts
=============================================================================
DATE: 23-Feb-2006
DOY: 054
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A Mechanism Lubrication was performed from 15:00 - 16:12 UT.
A primary parity error was detected at address #800074e3 - ML Parsers
Module - UNSAFE. A Reboot will be performed once keyhole operations end.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 24-Feb-2006
DOY: 055
OPERATIONS ENGINEER(S): C. Maroney
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 25-Feb-2006
DOY: 056
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 26-Feb-2006
DOY: 057
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 27-Feb-2006
DOY: 058
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 28-Feb-2006
DOY: 059
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
A telemetry submode change (from Submode 6 to 5) occured at 18:55 UT.
CDS nominal after submode change.
DAY PLAN: Keyhole Science Operations.
COMMENTS: 34M Keyhole starts.
=============================================================================
From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory Site maintained by John Rainnie. Last revised on Thursday (19/Jan/2006) at 11:09. |