February 1997
 
============================================================================== 
DATE:  1-Feb-1997 16:31:48
DOY: 032
OPERATIONS ENGINEER(S): G. Dimitoglou
SCIENTIST: R. Thomas/A. Fludra 
CDS INSTRUMENT: Nominal. 	 
CDS GROUND SYSTEM: Nominal. Changed disk from /cdsd3 to /cdsd4
DAY PLAN: Science Operations 
COMMENTS:
============================================================================== 
DATE:  2-Feb-1997 16:31:48
DOY: 033
OPERATIONS ENGINEER(S): G. Dimitoglou
SCIENTIST: R. Thomas/A. Fludra 
CDS INSTRUMENT: SEU detected on the primary and the secondary.  Both were 
 determined to be in an area such that the instrument could continue 
 temporarily with no problems.  The instrument will be rebooted when an
 optimal time arises. 
CDS GROUND SYSTEM: Nominal. Changed disk from /cdsr2 to /cdsr3.  
DAY PLAN: Science Operations 
COMMENTS:
==============================================================================
DATE:  3-Feb-1997 
DOY: 034
OPERATIONS ENGINEER(S): G. Dimitoglou
SCIENTIST: R. Thomas
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  4-Feb-1997 
DOY: 035
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: R. Thomas
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Changed the following raster durations:
 10/7 from 2510 to 2528
 11/7 from 537 to 542
 13/8 from 1304 to 1312
 14/1 from 1373 to 1403
 17/1 from 11531 to 11626
 34/10 from 5308 to 5335
 121/1 from 349 to 571
Imported study 151/1 USUN_10 to the EOF.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  5-Feb-1997 
DOY: 036
OPERATIONS ENGINEER(S): G. Dimitoglou/C. Haskell
SCIENTIST: R. Thomas
CDS INSTRUMENT: VDS Register A Failure recorded.  A convenient time was
 found to perform a reboot at 21:30 UT.  The instrument was rebooted with
 no problems.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  6-Feb-1997 
DOY: 037
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: R. Thomas
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  7-Feb-1997 
DOY: 038
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: R. Thomas
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  8-Feb-1997 
DOY: 039
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: D. Zarro
CDS INSTRUMENT: Secondary SEU, reboot was nominal.  
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  9-Feb-1997 
DOY: 040
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: D. Zarro
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  10-Feb-1997 
DOY: 041
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: 
  Nominal.
  First study of tommorows plan had to be started manually.
CDS GROUND SYSTEM: Made the following raster duration changes:
 10/21 from 5523 to 5598
 36/31 from 2144 to 2187
 123/1 from 706 to 716
 125/2 from 2471 to 2490
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  11-Feb-1997 
DOY: 042
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: 
  Watchdog error at 22:50 UT.  Due to end of DSN contact, the 
  instrument could not be rebooted until 05:30 UT Feb. 12.
  The reboot was nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  12-Feb-1997 
DOY: 043
OPERATIONS ENGINEER(S): G. Dimitoglou/R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
 Imported the study int_dist_18.def to the EOF.
 Made the following raster duration changes:
 	11/29 	from 	2699 	to 	2860
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  13-Feb-1997 
DOY: 044
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: D. Zarro
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
 Imported the study chms_19.def to the EOF.
 Made the following raster duration changes:
 	11/30 	from 	1199 	to 	1220
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  14-Feb-1997 
DOY: 045
OPERATIONS ENGINEER(S): G. Dimitoglou/R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  15-Feb-1997 
DOY: 046
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  A WATCHDOG error occured at 05:40 UT.  CDS was rebooted at 07:50 UT.
  The MCP voltage on each of the GIS detectors was incorrectly set during
  GIS studies today.  The MCP Voltage remained at parking throughout each
  study.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
  A SVM thermal reconfiguration occured at 10:14 UT. due to an instrument
  anomaly with CEPAC.  CEPAC was subsequently switched off.  The SVM swiched
  over to the REDUNDANT (B) side.  The switch back to the NOMINAL (A) side
  occured at ~20:00 UT 
==============================================================================
DATE:  16-Feb-1997 
DOY: 047
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  A WATCHDOG error occured at 07:57 UT.  CDS was rebooted at 12:25 UT.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  17-Feb-1997 
DOY: 048
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  Lube study performed.  During the lube study, a secondary event occurred.
  Secondary was rebooted and all was okay.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  18-Feb-1997 
DOY: 049
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  GIS did not run a study due to the HVs not being set via commands in the 
  series table.  A cpt patch is in the works to correct the problem.
CDS GROUND SYSTEM: Nominal. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  19-Feb-1997 
DOY: 050
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  Mail not working properly for some unknown reason.  GIS series tables 
  checked for missing commands - no problems found.  
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  20-Feb-1997 
DOY: 051
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal
CDS GROUND SYSTEM: 
  Mail is not currently working on any of the cds* machines.  The problem
  is still being resolved.  
  A software update was performed at 22:39 UT
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  21-Feb-1997 
DOY: 052
OPERATIONS ENGINEER(S): C. Haskell
SCIENTIST: W. Thompson
CDS INSTRUMENT: 
  Nominal.
CDS GROUND SYSTEM: Mail problem continues. 
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  22-Feb-1997
DOY: 053
OPERATIONS ENGINEER(S): G. Dimitoglou 
SCIENTIST: S. Matthews 
CDS INSTRUMENT:
   Watchdog Error. Rebooted. Nominal.
CDS GROUND SYSTEM: Mail problem continues.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  23-Feb-1997
DOY: 054
OPERATIONS ENGINEER(S): G. Dimitoglou
SCIENTIST: S. Matthews
CDS INSTRUMENT:
   VDS Error. Rebooted. Nominal.
CDS GROUND SYSTEM: Mail problem continues.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  24-Feb-1997
DOY: 055
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: S. Matthews
CDS INSTRUMENT:
  The NIS was incorrectly setup after it was rebooted on 97 DOY 54.  NIS
  science data from DOY 54 16:37UT to DOY 55 16:41UT was corrupted.  The
  safety of the detector was not compromised.
CDS GROUND SYSTEM: Mail problem was resolved.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  25-Feb-1997
DOY: 056
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: S. Matthews
CDS INSTRUMENT:
  A WATCHDOG error ocurred prior to 00:34 UT.  The instrument was rebooted
  at 01:04 UT.  Nominal after reboot.
CDS GROUND SYSTEM: Mail is not working again.  Updated the following raster
  durations:

	11/30 from 1220 to 1319
	103/1 from 2111 to 2154
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  26-Feb-1997
DOY: 057
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: S. Matthews
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Mail problem seems to be solved.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  27-Feb-1997
DOY: 058
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: S. Matthews
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  Problem discovered with the Jukebox being able to inventory tapes.  
  Currently unresolved.
DAY PLAN: Science Operations
COMMENTS:
==============================================================================
DATE:  28-Feb-1997
DOY: 059
OPERATIONS ENGINEER(S): C. Haskell/R. Yurow
SCIENTIST: S. Matthews
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
 Problem resolved with the networker.  
DAY PLAN: Science Operations
COMMENTS:
==============================================================================