Scientific Operations
 Front Page
 Scientific Ops
  » Plans
  » Pointings
  » Report
  » Requests
  » Log
  » Notes
  » Tech Info
 Engineering
 Software
 Results
 Gallery
 Atlas
 Press
 Links
 Project
 Newsletter
 Copyright
January 1996
 
===============================================================================
JANUARY 1, 1996 -- DOY 1

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 2, 1996 -- DOY 2

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 3, 1996 -- DOY 3

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 4, 1996 -- DOY 4

INSTRUMENT STATUS:  nominal 
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 5, 1996 -- DOY 5

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 6, 1996 -- DOY 6

INSTRUMENT STATUS:  nominal 
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 7, 1996 -- DOY 7

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 8, 1996 -- DOY 8

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 9, 1996 -- DOY 9

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS: nominal 
PLANNING:

=====
JANUARY 10, 1996 -- DOY 10

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 11 1996 -- DOY 11

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal  
PLANNING:

=====
JANUARY 12, 1996 -- DOY 12

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 13, 1996 -- DOY 13

INSTRUMENT STATUS:  nominal, QCM performed, duty cycle set to 80% from 90%
GROUND SYSTEM STATUS:   nominal
PLANNING:

=====
JANUARY 14, 1996 -- DOY 14

INSTRUMENT STATUS:  Patch test and table load dump
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 15, 1996 -- DOY 15

INSTRUMENT STATUS:  MCU commisioning begins
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 16, 1996 -- DOY 16

INSTRUMENT STATUS:  table loads & dumps 
GROUND SYSTEM STATUS:  installed alarm database 2.1, and new telem. & command
		       databases.

PLANNING:

=====
JANUARY 17, 1996 -- DOY 17

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 18, 1996 -- DOY 18

INSTRUMENT STATUS:  test CDHS and VDS software
GROUND SYSTEM STATUS:  nomianal
PLANNING:

=====
JANUARY 19, 1996 -- DOY 19

INSTRUMENT STATUS:  test GIS software, take VDS image with doors shut.
GROUND SYSTEM STATUS:
PLANNING:

=====
JANUARY 20, 1996 -- DOY 20

INSTRUMENT STATUS:  substitution heaters turned off, monitoring enabled
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 21, 1996 -- DOY 21

INSTRUMENT STATUS:  switch on GIS HV's, ramp up GIS HV's
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 22, 1996 -- DOY 22

INSTRUMENT STATUS:  ramp GIS HV's
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 23, 1996 -- DOY 23

INSTRUMENT STATUS:  set GIS detectors to parking voltage, ramp d1 and d2 for 1 
		    hr., d3 for 1/2 hour.
GROUND SYSTEM STATUS:  cron job created for emon.
PLANNING:

=====
JANUARY 24, 1996 -- DOY 24

INSTRUMENT STATUS:  complete GDC2 for detectors 3&4, and start GDC3.  Filament 
		    on.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 25, 1996 -- DOY 25

INSTRUMENT STATUS:  continued GDC3
GROUND SYSTEM STATUS:  backups begin, stm update for GIS raw data dump items.
PLANNING:

=====
JANUARY 26, 1996 -- DOY 26

INSTRUMENT STATUS:  GDC3 continued, VDS HV on.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 27, 1996 -- DOY 27

INSTRUMENT STATUS:  GIS GDC continued, VDS HV on.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 28, 1996 -- DOY 28

INSTRUMENT STATUS:  NIS lockout tests, HV on.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 29, 1996 -- DOY 29

INSTRUMENT STATUS:  Completed GIS detector commissioning.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 30, 1996 -- DOY 30

INSTRUMENT STATUS:  complete GIS detector commissioning, start VDS
		    commissioning
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
JANUARY 31, 1996 -- DOY 31

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:








From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory
Site maintained by John Rainnie.
Last revised on Tuesday (17/Jul/2001) at 09:05.