DATE:01-July-2000
DOY: 183
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.  
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:02-July-2000
DOY: 184
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.  
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:03-July-2000
DOY: 185
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  FFCAL was inadvertantly scheduled at 13:30 UT when no operational support
  was available.  
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:04-July-2000
DOY: 186
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A parity error was detected in the secondary (science) processor memory
  space.  
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:05-July-2000
DOY: 187
OPERATIONS ENGINEER(S):  C. Maroney
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS:
=============================================================================
DATE:06-July-2000
DOY: 188
OPERATIONS ENGINEER(S):  C. Maroney / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A Lubrication study was completed at 16:30 UT.
  The NIS was reset at 16:50 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Lube study, NIS reset, Science Observations.
COMMENTS:
=============================================================================
DATE:07-July-2000
DOY: 189
OPERATIONS ENGINEER(S):  C. Maroney
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A Flat Field Calibration study was completed at 17:00 UT.
  GIS detectors 1 and 3 TRIPPED ~17:25 UT due to the FFCAL script 
over-running its cooperative study.  The GIS detectors CBGHV1V and 
CBGHV3V were reset and enabled to their parking voltages at 17:36 UT.
Pending further investigation.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: FFCAL, Science Observations.
COMMENTS: 
=============================================================================
DATE:08-July-2000
DOY: 190
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:09-July-2000
DOY: 191
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:10-July-2000
DOY: 192
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:11-July-2000
DOY: 193
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:12-July-2000
DOY: 194
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  A telemtry submode switch from submode 6 to submode 5 occured at 19:17 UT.
CDS is nominal after the submode switch.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:13-July-2000
DOY: 195
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Observations.
COMMENTS: 
=============================================================================
DATE:14-July-2000
DOY: 196
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A +X5 flare occured at ~10:00 UT.  A Proton event as to was associated
with the flare.  The science plan was aborted at 15:33 UT due to the proton
event.  The NIS HV was disabled was a precautionary measure.
  A primary event error was detected at #800017af.  Parity error is in the
BOOTSTRAP module.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Instrument Monitoring.
COMMENTS: 
=============================================================================
DATE:15-July-2000
DOY: 197
OPERATIONS ENGINEER(S):  R. Yurow / W. Hammond
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A parity error was detected in the primary processor memory space.  The
  parity error is located in the deffered module, which requires a patch
  reload in order to clear.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Instrument Monitoring.
COMMENTS: 
=============================================================================
DATE:16-July-2000
DOY: 198
OPERATIONS ENGINEER(S):  R. Yurow / B. Donaldson
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  An attempt was made to reboot CDS and reload all CDHS patches.  The CDS 
  reboot began at 19:02 UT with a cold start, since there was a previous
  error in the bootstrap module.  However, commands to reload patches were
  rejected by the CMS due a syntax error in the command blocks.  The problem
  was traced to an error in the Perl script which supports patching.  CDS
  was then recovered back to READY_BOTH with the science processor disabled,
  the NIS HV turned off and no patches.  
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Instrument Monitoring.
COMMENTS: 
=============================================================================
DATE:17-July-2000
DOY: 199
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: R. Harrison
CDS INSTRUMENT: 
  CDS doors were closed at 21:12 UT in preparation for S/C maneuvers.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Close Doors, Instrument Monitoring.
COMMENTS: 
=============================================================================
DATE:18-July-2000
DOY: 200
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: R. Harrison
CDS INSTRUMENT: 
  The Perl script was able to send commands through the backup CMS to the
spacecraft simulator.  Results have been sent to RAL for analysis.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Spacecraft Maneuvers, Instrument Monitoring.
COMMENTS: 
=============================================================================
DATE:19-July-2000
DOY: 201
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: R. Harrison
CDS INSTRUMENT: 
  CDS was recovered to READY_BOTH and recovery operations were completed
at 20:25 UT.
  Doors were opened at 21:28 UT and the science plan was resumed at 23:00 UT
with SYNOP (Instrument temperatures still cold).
CDS GROUND SYSTEM: Nominal.
DAY PLAN: CDS recovery, Instrument Monitoring.
COMMENTS: 
=============================================================================
DATE:20-July-2000
DOY: 202
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: R. Harrison
CDS INSTRUMENT: 
  FFCAL was started at 22:06, failed at about 22:48 due to loss of
commanding.
CDS GROUND SYSTEM: 
  Due to UPS maintenance CDSo7 and CDSo9 unexpectedly lossed power at
17:40 UT.  SOC and other teams experienced the outage.  TLM was resumed at
17:35 UT.  CDS equipment nominal.
DAY PLAN: Flat Field Calibration, Science Operations.
COMMENTS: Temperatures nominal.
=============================================================================
DATE:21-July-2000
DOY: 203
OPERATIONS ENGINEER(S):  C. Maroney
SCIENTIST: R. Harrison
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:22-July-2000
DOY: 204
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: R. Harrison
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:23-July-2000
DOY: 205
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: R. Harrison
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:24-July-2000
DOY: 206
OPERATIONS ENGINEER(S):  C. Maroney
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:25-July-2000
DOY: 207
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:26-July-2000
DOY: 208
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:27-July-2000
DOY: 209
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:28-July-2000
DOY: 210
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:29-July-2000
DOY: 211
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  A software update was performed and confirmed at 21:30 UT.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:30-July-2000
DOY: 212
OPERATIONS ENGINEER(S):  C. Maroney / W. Hammond
SCIENTIST: J. Brosius
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE:31-July-2000
DOY: 213
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A mechanism lubrication study was completed at 23:33 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Lubrication, Science Operations.
COMMENTS:
=============================================================================












From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory