DATE: 1-Jun-2008
DOY: 153
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Chris Maroney (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 2-Jun-2008
DOY: 154
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Danielle Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 3-Jun-2008
DOY: 155
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST:  Danielle Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 4-Jun-2008
DOY: 156
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Danielle Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 5-Jun-2008
DOY: 157
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Danielle Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 6-Jun-2008
DOY: 158
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Danielle Bewsher (RAL)
CDS INSTRUMENT: 
  A primary parity error was detected at #8005bbd3 - SAFE.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 7-Jun-2008
DOY: 159
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST:  Danielle Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 8-Jun-2008
DOY: 160
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Danielle Bewsher (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 9-Jun-2008
DOY: 161
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 10-Jun-2008
DOY: 162
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 11-Jun-2008
DOY: 163
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: 
  A secondary parity error was detected at #800479bb.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 12-Jun-2008
DOY: 164
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 13-Jun-2008
DOY: 165
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: 
  A Mechanism Lubrication was performed at 07:00 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 14-Jun-2008
DOY: 166
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: 
  Primary parity error was detected at #800166d7-Two Transputer Module(SAFE).
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 15-Jun-2008
DOY: 167
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST:  Andrzej Fludra (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 16-Jun-2008
DOY: 168
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 17-Jun-2008
DOY: 169
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 18-Jun-2008
DOY: 170
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: 
  A CDS Reboot was initiated by CB3RESET at 16:35 UT.  CDS was returned to
READY_BOTH at 17:30 UT.  Reboot procedure was completed at 18:01 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 19-Jun-2008
DOY: 171
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  A telemetry submode change (6 to 5) occurred at 15:10 UT.  CDS Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 20-Jun-2008
DOY: 172
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 21-Jun-2008
DOY: 173
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 22-Jun-2008
DOY: 174
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Terry Kucera (GSFC)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 23-Jun-2008
DOY: 175
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST:  John Rainnie (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 24-Jun-2008
DOY: 176
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: John Rainnie (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 25-Jun-2008
DOY: 177
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: John Rainnie (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 26-Jun-2008
DOY: 178
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: John Rainnie (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 27-Jun-2008
DOY: 179
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: John Rainnie (RAL)
CDS INSTRUMENT: 
  A secondary parity error was detected at #80060157.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 28-Jun-2008
DOY: 180
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: John Rainnie (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 29-Jun-2008
DOY: 181
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: John Rainnie (RAL)
CDS INSTRUMENT: 
  A Mechanism Lubrication was performed at 07:00 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================
DATE: 30-Jun-2008
DOY: 182
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: Andrzej Fludra (RAL)
CDS INSTRUMENT: 
  A Primary parity error was detected at #800500f3 - Science Module(SAFE).
  A Secondary parity error was detected at #8007e04f.
  At approximately 18:45 UT, while loading a plan, CDS stopped responding to
commands generating OBDH errors when commanding was attempted.  Multiple attempts
to send the pari of commands required to reset CDS failed, possible du to network
issues.  Finally, at ~20:16 UT, CDS was successfully rebooted.
  Recovery operations proceeded normally until 21:31 UT, when it was attempted to
go to READY_BOTH.  At this time the GIS powered up in a state in which it could
not receive commands and could not generate housekeeping packets.
  Multiple attempts to reset the GIS were ineffective as was an attempt to run
GIS patching script, turning off the 5V and 12V inputs and returning back to
STANDBY then going to READY_BOTH.
  Finally, at 23:38 UT, a complete CDS reset was started.  This was successful in
returning the GIS to a known state.  Recovery operations were completed at
02:11 UT (DOY 183).  CDS will remain idle overnight.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
==============================================================================


From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory
Site maintained by John Rainnie.