May 1996
 
===============================================================================
MAY 1, 1996 -- DOY 122

INSTRUMENT STATUS:  Test study test6_1/v3 for raster durations
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 2, 1996 -- DOY 123

INSTRUMENT STATUS:  Watchdog error, CDS rebooted back to Standby.  CDS was 
		    rebooted and is now nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 3, 1996 -- DOY 124

INSTRUMENT STATUS:  Sequence counter fiasco.  The counter was accidentally
		    bumped up 700 or so studies.  It will be left where it is
		    now, and studies will increment from that point on.
GROUND SYSTEM STATUS:  s/w update.
PLANNING:

=====
MAY 4, 1996 -- DOY 125

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 5, 1996 -- DOY 126

INSTRUMENT STATUS:  Problem after NIS engineering work in which studies were
                    overwritten by things that were uploaded.  A couple studies
		    were lost in the process.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 6, 1996 -- DOY 127

INSTRUMENT STATUS:  GIS raw dumps taken.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 7, 1996 -- DOY 128

INSTRUMENT STATUS:  Problem with command link while loading a plan.  Plan was
		    reloaded later.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 8, 1996 -- DOY 129

INSTRUMENT STATUS:  GIS raw dumps.
GROUND SYSTEM STATUS:  imported NIMCPO_1, and changed disk to /cdsd5.
PLANNING:

=====
MAY 9, 1996 -- DOY 130

INSTRUMENT STATUS:  GIS raw dumps.
GROUND SYSTEM STATUS:  s/w update
PLANNING:

=====
MAY 10, 1996 -- DOY 131

INSTRUMENT STATUS:  GIS raw dumps.  Secondary SEU - secondary rebooted, feature
		    tracking run.
GROUND SYSTEM STATUS:  imported into EOF:  chrom_n1_16, chrom_n2_1, net14, 
                       net24, nfctr_6, scatter_1, fillfacn_10
PLANNING:

=====
MAY 11 1996 -- DOY 132

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  Switched ECS display to run from CDS7 instead of CDS8
PLANNING:

=====
MAY 12, 1996 -- DOY 133

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 13, 1996 -- DOY 134

INSTRUMENT STATUS:  NIS engineering
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 14, 1996 -- DOY 135

INSTRUMENT STATUS:  Watchdog error, CDS rebooted nominally
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 15, 1996 -- DOY 136

INSTRUMENT STATUS:  TGRAD study tested
GROUND SYSTEM STATUS:  s/w update
PLANNING:

=====
MAY 16, 1996 -- DOY 137

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 17, 1996 -- DOY 138

INSTRUMENT STATUS:  doors shut for momentum management at 20:20 UT.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 18, 1996 -- DOY 139

INSTRUMENT STATUS:  Doors still closed, GIS filament dumps performed, VDS door
		    opened at 23:45 UT.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 19, 1996 -- DOY 140

INSTRUMENT STATUS:  3 SEU's reported, 2 on primary, 1 on VDS.  VDS rebooted, 
	            GIS filament dumps done, GIS door opened at 02:10 UT.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 20, 1996 -- DOY 141

INSTRUMENT STATUS:  feature tracking run again, primary rebooted due to 
	            SEU hits the day before, rebooted nominally.
GROUND SYSTEM STATUS:  DCS_edit used to edit the start of JOP002.
PLANNING:

=====
MAY 21, 1996 -- DOY 142

INSTRUMENT STATUS:  TGRAD run, 90 degree spacecraft roll performed
GROUND SYSTEM STATUS:  New telemtry database installed, version 5.3
PLANNING:

=====
MAY 22, 1996 -- DOY 143

INSTRUMENT STATUS:  Doors shut for orbit trim at 16:00 UT, GIS filament dumps
		    performed.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 23, 1996 -- DOY 144

INSTRUMENT STATUS:  Filament dumps completed, GIS and NIS doors opened at 00:00
	            UT (tomorrow).  
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 24, 1996 -- DOY 145

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 25, 1996 -- DOY 146

INSTRUMENT STATUS:  GIS raw dumps
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 26, 1996 -- DOY 147

INSTRUMENT STATUS:  nominal, test of pointing to 20'.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 27, 1996 -- DOY 148

INSTRUMENT STATUS:  tested lube study, secondary SEU reported.
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 28, 1996 -- DOY 149

INSTRUMENT STATUS:  GIS raw dumps on the off limb
GROUND SYSTEM STATUS:  nominal
PLANNING:

=====
MAY 29, 1996 -- DOY 150

INSTRUMENT STATUS:  test feature tracking, GIS raw dumps off limb
GROUND SYSTEM STATUS:
PLANNING:

=====
MAY 30, 1996 -- DOY 151
 
INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  tar'd /cdsfits to tape, deleted files on /cdsd2, /cdsd3,
		       /cdsd4, /cdsr1, and /cdsr2, and added soho-arch01 to all
		       IWS's
PLANNING:

=====
MAY 31, 1996 -- DOY 152

INSTRUMENT STATUS:  nominal
GROUND SYSTEM STATUS:  nominal
PLANNING: