DATE: 1-Oct-2004
DOY: 275
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Limited (Keyhole) Science Operations.
COMMENTS:
=============================================================================
DATE: 2-Oct-2004
DOY: 276
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 3-Oct-2004
DOY: 277
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: D. Bewsher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 4-Oct-2004
DOY: 278
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 5-Oct-2004
DOY: 279
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 6-Oct-2004
DOY: 280
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following study was imported to the EOF:
efinar_1_69.def.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 7-Oct-2004
DOY: 281
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
The science plan was aborted at 10:31 UT due to a corrupted series table
(series_25). The plan was later reloaded (with new tables) and will continue
at 18:00 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 8-Oct-2004
DOY: 282
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 9-Oct-2004
DOY: 283
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 10-Oct-2004
DOY: 284
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 11-Oct-2004
DOY: 285
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
One run of FFCAL was completed at 21:42 UT. The script was aborted
shortly before the end of the study, because the script was only starting
its 2nd run of FFCAL and there was insufficient time.
CDS GROUND SYSTEM:
The following raster duration changes were made:
EFINAR_1 ID/10 VAR/79 3185s - 3230s
ARCONT_1 ID/11 VAR/95 1480s - 1500s
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 12-Oct-2004
DOY: 286
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following studies were imported to the EOF:
gis_sq_1.def ID/ 22 VAR/ 2
xpb_tw1_4.def ID/160 VAR/ 4
xbp_tw2_13.def ID/ 17 VAR/13
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 13-Oct-2004
DOY: 287
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 14-Oct-2004
DOY: 288
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 15-Oct-2004
DOY: 289
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A parity error was detected at address location #80079eef in the Primary
processor memory space.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 16-Oct-2004
DOY: 290
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 17-Oct-2004
DOY: 291
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 18-Oct-2004
DOY: 292
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following raster duration change was made:
STRE4W rid/11 var/120 5750s - 6150s
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 19-Oct-2004
DOY: 293
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 20-Oct-2004
DOY: 294
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A primary memory error was detected at address #8001bfaf.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 21-Oct-2004
DOY: 295
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 22-Oct-2004
DOY: 296
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 23-Oct-2004
DOY: 297
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 24-Oct-2004
DOY: 298
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT:
A secondary memory error was detected at address #80069cef.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 25-Oct-2004
DOY: 299
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Lang
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
The following raster duration change was made:
XBP_TW1 rid/92 var/6 607s - 630s.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 26-Oct-2004
DOY: 300
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Lang
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 27-Oct-2004
DOY: 301
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Lang
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 28-Oct-2004
DOY: 302
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Lang
CDS INSTRUMENT:
An onboard run of a Mechanism Lubrication was completed at 22:41 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 29-Oct-2004
DOY: 303
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: J. Lang
CDS INSTRUMENT:
A parity error in the primary processor memory space was detected at
address #80079eef - Packetization Module - SAFE.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 30-Oct-2004
DOY: 304
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: J. Lang
CDS INSTRUMENT:
A parity error in the primary processor memory space was detected at
address #8001bfaf - Compression Module - SAFE.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 31-Oct-2004
DOY: 305
OPERATIONS ENGINEER(S): B. Howell / C. King
SCIENTIST: J. Lang
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================