October 1999
 
=============================================================================
DATE: 1-Oct-1999
DOY: 274
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: C. Maroney
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  GIS raw files catalogued.
DAY PLAN: No activities planned.
COMMENTS:
=============================================================================
DATE: 2-Oct-1999
DOY: 275
OPERATIONS ENGINEER(S):  W. Hammond / E. Donaldson
SCIENTIST: C. Maroney
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: No activities planned.
COMMENTS:
=============================================================================
DATE: 3-Oct-1999
DOY: 276
OPERATIONS ENGINEER(S):  W. Hammond / E. Donaldson
SCIENTIST: C. Maroney
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: No activities planned.
COMMENTS:
=============================================================================
DATE: 4-Oct-1999
DOY: 277
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: C. Maroney
CDS INSTRUMENT: 
  CDS substitution heaters were turned off at 18:12 UT.
  CDS recovered to Ready_Both at 19:51 UT.
  GIS Filament Dumps were performed from 20:00 UT to 01:00 UT DOY 278.
CDS GROUND SYSTEM: 
  Reverted to IDL 4.1 on CDS cluster.
DAY PLAN: Submode Switch, CDS heaters OFF, Recover to Ready_Both mode.
COMMENTS: If anytime left: GIS Filament Dumps
=============================================================================
DATE: 5-Oct-1999
DOY: 278
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: S. Patsourakos
CDS INSTRUMENT: 
  GIS Filament Dumps were performed from 13:30 UT to 17:00 UT
  CDS Doors were opened at 17:13 UT
  GIS Raw Dumps were performed from 17:30 UT to 21:00 UT
  A lubrication study was completed at 22:30 UT
CDS GROUND SYSTEM: Nominal.
DAY PLAN: GIS Calibration, Lubrication Study, Open Doors
COMMENTS:
=============================================================================
DATE: 6-Oct-1999
DOY: 279
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: S. Patsourakos
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  Imported study qs_dem_2_11.def.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 7-Oct-1999
DOY: 280
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: S. Patsourakos
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  A software update was performed.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 8-Oct-1999
DOY: 281
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: S. Patsourakos
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  GIS filament raw files were catalogued.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 9-Oct-1999
DOY: 282
OPERATIONS ENGINEER(S):  E. Donaldson
SCIENTIST: S. Patsourakos
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 10-Oct-1999
DOY: 283
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: S. Patsourakos
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 11-Oct-1999
DOY: 284
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: D. Pike
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 12-Oct-1999
DOY: 285
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: D. Pike
CDS INSTRUMENT: 
  An NIS setup register A failure system error occured.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 13-Oct-1999
DOY: 286
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: D. Pike
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 14-Oct-1999
DOY: 287
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: D. Pike
CDS INSTRUMENT: 
  A parity error was detected in the primary processor memory space.  Since
  error is in a safe location, no reboot is necessary.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 15-Oct-1999
DOY: 288
OPERATIONS ENGINEER(S):  C. Maroney
SCIENTIST: D. Pike
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  Imported study arintera_53.def.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 16-Oct-1999
DOY: 289
OPERATIONS ENGINEER(S):  E. Donaldson
SCIENTIST: D. Pike
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 17-Oct-1999
DOY: 290
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: D. Pike
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 18-Oct-1999
DOY: 291
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: L. Green
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 19-Oct-1999
DOY: 292
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: L. Green
CDS INSTRUMENT:
  The science plan was aborted at 20:01 UT in order to observe a C9 flare.
  At 20:07 UT the study MPIFLAR2 was started at the wrong location due to 
  errors calculating the pointing and using the wrong slit (6 instead of 1).
  GIS detectors 1, 3, 4 triped at 20:10 due to excessive count rates.  All 
  three detectors were reset by 20:12.  The MPIFLAR2 study was rerun at 
  20:14 with the correct slit, but still at the wrong location, at 20:12. 
  The normal science plan was resumed at 21:40 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 20-Oct-1999
DOY: 293
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: L. Green
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
  The following study was imported to the EOF:
	merc4_8.def
  The EOF cluster was upgraded to IDL version 5.2.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 21-Oct-1999
DOY: 294
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: L. Green
CDS INSTRUMENT: 
  One run of FFCAL, the NIS flat field study was started at 19:21 UT.  At
  20:00 UT, FFCAL was interupted to begin flare observations.  The study
  MPIFLAR2 was run at 20:07 UT on what was thought to be a C6 flar.  The
  science plan was resumed at 22:00 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 22-Oct-1999
DOY: 295
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: L. Green
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 23-Oct-1999
DOY: 296
OPERATIONS ENGINEER(S):  E. Donaldson
SCIENTIST: L. Green
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 24-Oct-1999
DOY: 297
OPERATIONS ENGINEER(S):  W. Hammond
SCIENTIST: L. Green
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 25-Oct-1999
DOY: 298
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: T. Fredvik
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 26-Oct-1999
DOY: 299
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: T. Fredvik
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 27-Oct-1999
DOY: 300
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: T. Fredvik
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM:
  The following GSETs were created:
	Zone 1	Slit 1	GSET ID 58 
	Zone 1	Slit 2	GSET ID 62 
	Zone 1	Slit 3	GSET ID 61 
	Zone 1	Slit 4	GSET ID 63 
	Zone 1	Slit 5	GSET ID 64 
DAY PLAN: Science Operations.
COMMENTS:
==============================================================================
DATE: 28-Oct-1999
DOY: 301
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: T. Fredvik
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  The following studies were imported to the EOF:
	gfec_9.def	Study ID 217 / Var 8
	gissm4_5.def	Study ID 215 / Var 5
	gsm4_8.def	Study ID 217 / Var 9
	n_u2_5.def	Study ID 113 / Var 5
	pobs1_2_46.def	Study ID 44  / Var 46
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 29-Oct-1999
DOY: 302
OPERATIONS ENGINEER(S):  R. Yurow / C. Maroney
SCIENTIST: T. Fredvik
CDS INSTRUMENT: 
  A telemetry submode change from submode 5 (CDS medium rate) to submode 4
  (CDS low rate) occurred at 20:02 UT.
  A telemetry submode change from submode 4 (CDS low rate) to submode 5
  (CDS medium rate) occurred at 20:13 UT.
  A telemetry submode change from submode 5 (CDS medium rate) to submode 4
  (CDS low rate) occurred at 20:49 UT.
  A mechanism lubrication study was completed at 22:29 UT.
  The NIS was reset at 22:49 UT clear the error status word.
  At 23:17 UT the CDHS crashed while uplinking the science plan for the 
  weekend.  The crash caused caused toggle bit errors on all subsequent 
  commands sent after the crash. CDS was reset at 00:24 UT DOY 303 and the
  LOBT was sent at 00:32 UT DOY 303.  During the reset, CDS came up on
  processor 1 resulting in a loss of all of the patched program modules.
  CDS was therefore put in a safe state until recovery efforts could 
  continue on DOY 303.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 30-Oct-1999
DOY: 303
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: T. Fredvik
CDS INSTRUMENT: 
  CDS was returned to SNOOZE mode at 16:27 UT in order to begin uploading
  the CDHS patches which had been lost during the recovery of the previous
  day.  All 4 patches were reloaded by 17:15 UT, however a subsequent memory
  showed the defered module also appearing in the extended module list.
  Given the difficulties with doing a memory dump in telemetry submode 4, it
  was decided to continue on with the recovery.  In addtion to reloading the
  CDHS patches, all 3 GIS were also reloaded in order to bring the GIS
  software up to version 2.6. Reboot procedures were completed at 19:41 UT 
  and the science plan was resumed 20:20 UT, albeit with the wrong GSET due
  to a bug in CPT.
  A parity error was detected in the primary processor memory space at
  23:22 UT.  Since the error was in a safe location, no reboot was necessary.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================
DATE: 31-Oct-1999
DOY: 304
OPERATIONS ENGINEER(S):  R. Yurow
SCIENTIST: T. Fredvik
CDS INSTRUMENT: 
  GIS detector 1 tripped at 2:47 UT, probably due to doing off limb
  observations with the wrong GSET.  
  The FOT reported that CTM31 began flagging intermittently.  This was caused
  by an elavated spacecraft panel temperature (~22.0 C).
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS:
=============================================================================









From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory