September 2003
 
=============================================================================
DATE:1-Sep-2003
DOY: 244
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:2-Sep-2003
DOY: 245
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  The following changes were made to raster duration times:
    G2NS     (RID/126 ,Var/2)  1286s - 1300s
    G2AL_V4B (RID/231, Var/1)  5570s - 5580s
    BP_W_1   (RID/13, Var/24)   630s -  640s.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:3-Sep-2003
DOY: 246
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: 
  A Mechanism lubrication was completed at 00:19 UT (DOY 247).
CDS GROUND SYSTEM: 
  SOC System Failover testing was conducted from 14-17 UT (During a gap in
telemetry).  SOC/CDS ground systems nominal.
DAY PLAN: Mechanism Lubrication, Science Operations.
COMMENTS: 
=============================================================================
DATE:4-Sep-2003
DOY: 247
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:5-Sep-2003
DOY: 248
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: 
  A Flat Field Calibrations was run at 22:13 UT.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:6-Sep-2003
DOY: 249
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:7-Sep-2003
DOY: 250
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: P. Young (RAL)
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:8-Sep-2003
DOY: 251
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A parity error was detected in the Secondary memory space at address
#8000715b.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:9-Sep-2003
DOY: 252
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  A NIS Setup Register A Failure was detected.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:10-Sep-2003
DOY: 253
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: 
  The wavecal's for GIS GSETS 73 & 76 were updated.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:11-Sep-2003
DOY: 254
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:12-Sep-2003
DOY: 255
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:13-Sep-2003
DOY: 256
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:14-Sep-2003
DOY: 257
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: T. Kucera
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:15-Sep-2003
DOY: 258
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:16-Sep-2003
DOY: 259
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  At 20:20 UT, the IWS software was restarted due to a lost connection 
between cdso7 and the SOC machines.  Previously, during the gap (16:50 - 
20:15 UT), SOCs were performing Fail-Over testing.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:17-Sep-2003
DOY: 260
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
  A 4-day science plan was uploaded in case operations become impossible
during hurricane Isabel.
=============================================================================
DATE:18-Sep-2003
DOY: 261
OPERATIONS ENGINEER(S): C. Maroney
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
  Goddard closed at noon due to increased weather conditions of Isabel.
=============================================================================
DATE:19-Sep-2003
DOY: 262
OPERATIONS ENGINEER(S): R. Yurow
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: 
  All of the CDS operations machines were taken down and rebooted at 23:05 UT
to clear an error on cdso8.
DAY PLAN: Science Operations.
COMMENTS: 
  Goddard closed due to hurricane Isabel.
=============================================================================
DATE:20-Sep-2003
DOY: 263
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:21-Sep-2003
DOY: 264
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: P. Gallagher
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:22-Sep-2003
DOY: 265
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:23-Sep-2003
DOY: 266
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:24-Sep-2003
DOY: 267
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:25-Sep-2003
DOY: 268
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:26-Sep-2003
DOY: 269
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:27-Sep-2003
DOY: 270
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: A. Fludra
CDS INSTRUMENT: 
  A parity error was detected in the Secondary (Science) Processor at memory
location #80077037.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:28-Sep-2003
DOY: 271
OPERATIONS ENGINEER(S): J. Seidel / C. King
SCIENTIST: A. Fludra
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:29-Sep-2003
DOY: 272
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================
DATE:30-Sep-2003
DOY: 273
OPERATIONS ENGINEER(S): C. Maroney / R. Yurow
SCIENTIST: W. Thompson
CDS INSTRUMENT: Nominal.
CDS GROUND SYSTEM: Nominal.
DAY PLAN: Science Operations.
COMMENTS: 
=============================================================================


From the CDS Operations Management Team in the Space Science & Technology Department at CCLRC Rutherford Appleton Laboratory
Site maintained by John Rainnie.
Last revised on Tuesday (17/Jul/2001) at 08:55.